The Executive Engineer Medium Project Division Osmanabad v. Manubai W/o Ramchandra More
Case brief
What is this about?
Land acquisition; interest start date; Sections 28 and 34, Land Acquisition Act; interest payable from date of award under Section 11, not from date of notification or date of possession; Full Bench ruling in State of Maharashtra Vs. Kailash Shiva Rangari [2016 AIR (Bom.) 141] followed; Reference Court judgments and awards modified; first appeals partly allowed; deposits with accrued interest to be disbursed to claimants; stay applications disposed; High Court of Bombay, Aurangabad Bench; Shailesh P. Brahme, J.; decided 05.05.2026.
What did the court decide?
First appeals allowed partly: impugned judgments and awards of the Reference Court modified so that interest under Sections 28 and 34 of the Land Acquisition Act runs from the date of award under Section 11 and not from the date of notification, with the rest of each award left unaltered; amounts deposited in this Court or the Reference Court to be disbursed to the respondents/claimants with accrued interest; civil applications for stay disposed of.