Deputy Chief Engineer (Construction) Central Railway, Ajni, Nagpur v. Shri. Dhanraj Daulatrao Ghubade and Others
Case brief
What is this about?
Bombay High Court Nagpur Bench; CAF 813/2025 and CAF 3762/2025 in First Appeal (St.) 22482/2024; condonation of delay 943 days; statutory appeal; Central Railway Deputy Chief Engineer (Const.) Ajni Nagpur; land acquisition compensation withdrawal 75%; 50% undertaking 25% solvent surety; Rs.3,000 cost; Public Welfare Account; SMPIL No.01/2021 order dated 12.01.2026; Registrar (Judicial); Covid-19 delay; Prafulla S. Khubalkar, J.; order dated 14.01.2026; appeal admitted; private paper book eight weeks; Dhanraj Daulatrao Ghubade.
What did the court decide?
Civil Application No.813 of 2025 allowed and disposed of: delay of 943 days in filing the statutory appeal condoned subject to cost of Rs.3,000/- to be deposited in the 'Public Welfare Account' within two weeks. Civil Application No.3762 of 2025 allowed and disposed of: respondent No.1/claimant permitted to withdraw 75% of the deposited amount with accrued interest (50% on usual undertaking; 25% on solvent surety/security to the satisfaction of the Registrar (Judicial)). First Appeal (St.) No.22482 of 2024 admitted; Record and Proceedings called; appellant to file private paper book within eight weeks.