V.I.D.C., Thr. Executive Engineer, Minor Irrigation Division, Karanja v. Rajendra Haribhau Khadare and Others
Case brief
What is this about?
Land acquisition compensation withdrawal; 75% of deposited compensation released to original claimant/respondent No.1; 50% payable on usual undertaking, 25% on solvent surety; parity with order dated 16.02.2026 in Civil Application No.955 of 2026; compensation deposited by appellant Executive Engineer, Minor Irrigation Division, Karanja, Washim (V.I.D.C.); First Appeal No.1011 of 2025; Civil Application No.1041 of 2026; Bombay High Court Nagpur Bench; Justice Prafulla S. Khubalkar; decided 10th April 2026; M.A. Kadu advocate for applicant; P.T. Joshi AGP for respondent Nos.2 and 3/State; Rajendra Haribhau Khandare and others.
What did the court decide?
Withdrawal of 75% of the deposited compensation permitted to the original claimant/respondent No.1 - 50% on furnishing the usual undertaking and 25% on furnishing a solvent surety; civil application allowed and disposed of accordingly.