The Executive Engineer and Ors. v. Bajirao Gangaram Phad
Case brief
What is this about?
condonation of delay; setting aside abatement; legal representatives (LRs) brought on record; deceased appellant; land acquisition compensation; Acquiring Body; Executive Engineer Latur Minor Irrigation Division; withdrawal of deposited amount with accrued interest; undertaking to Registrar (Judicial); 12 weeks time to deposit; 50% amount deposited; Bombay High Court Aurangabad Bench; Shailesh P. Brahme; 2026:BHC-AUG:19600; FAST/24850/2024; civil applications 2026 and 2024 batch
What did the court decide?
Delay condoned and abatement set aside with leave to amend to bring the LRs of deceased appellants on record (CAs 4892/2026 and 4893/2026); delay of the Acquiring Body in its appeals condoned; claimant-applicants permitted to withdraw the deposited amounts with accrued interest on furnishing undertaking to the Registrar (Judicial); 12 weeks' time granted to the Acquiring Body to deposit the amount.