Satyanarayan Dattaram Patil and Others v. The Project Director National Highway Authority of India and Anr.
Case brief
What is this about?
Extension of arbitrator's mandate; Section 29-A of the Arbitration and Conciliation Act, 1996; Section 3G(5) of the National Highways Act, 1956; NHAI arbitration applications; disposal of batched applications; National Highway Authority of India v. Suresh Pardharinath Matre, MANU/MH/2637/2026; Jagdeep Chowgule v. Sheela Chowgule (SC, 29.01.2026); Chief Engineer (NH) PWD (Roads) v. BSC&C and C JV, 2024 SCC OnLine SC 1801; Aurangabad Bench; Arun R. Pedneker J. Relevant to queries on whether Section 29-A applies to arbitrations under Section 3G(5) of the National Highways Act.
What did the court decide?
All Arbitration Applications disposed of, with direction to the Arbitrator to decide the pending Arbitration Applications expeditiously; the interim Civil Applications were also disposed of. ¶¶147