The M. K. v. D. C., Thr., Exe. Eng., Sina Kolegaon Project, Paranda,Paranda,Osmanabad and Ors. v Kaishalyabai W/O Digambar Ghogare(Died), through Her L.Rs. Umesh S/O Gajendra Patil
Case brief
What is this about?
Kaishalyabai Digambar Ghogare (died) her LRs v. Executive Engineer; Civil Application No. 2859 of 2026 in FAST/33531/2023 with CAs 1440-1445 of 2024 in FAST/33531/2023, FAST/33536/2023, FAST/33540/2023; High Court of Judicature at Bombay, Aurangabad Bench; Shailesh P. Brahme, J.; decided 13.03.2026; withdrawal of deposited compensation Rs. 1,90,14,918/-; release of 75% with accrued interest on undertaking to Registrar (Judicial); retention of 25% to safeguard acquiring body; investment in nationalized bank; reliance on coordinate-bench order in First Appeal No. 82 of 2024; condonation of delay in preferring first appeals; first appeals admitted; ad-interim relief confirmed; land acquisition enhancement; advocates Vaishali Arun Shinde, S. N. Morampalle (AGP), Anil M. Gaikwad.
What did the court decide?
Lead civil application partly allowed: applicant to receive 75% of Rs. 1,90,14,918/- with accrued interest on furnishing undertaking to the satisfaction of the Registrar (Judicial); remaining 25% withheld to safeguard the acquiring body and balance invested in a nationalized bank. Civil applications for delay allowed (delay in first appeals condoned). First appeals admitted, Record and Proceedings called for, printing dispensed with. Civil applications for stay disposed of with earlier ad-interim relief confirmed.