Laxman Namdeo Shelke Died Lrs Ramkavar Laxman Shelke v. the Union of India through the General Manager Central Railway Chhatrapati Shivaji Terminus
Case brief
What is this about?
Land acquisition compensation reference FAST/32033/2024, Bombay High Court Aurangabad Bench, decided 06.01.2026 by Shailesh P. Brahme J. Claimant side (LRs of Laxman Namdeo Shelke) allowed to withdraw deposited amount of Rs. 4,09,082 with accrued interest on undertaking to Registrar (Judicial); condonation of 633 days delay in first appeal granted (no serious contest, no mala fides); first appeal admitted, record called, final disposal listed for 12.02.2026; ad interim relief confirmed as Acquiring Body deposited entire compensation with interest. Respondent: Union of India through General Manager, Central Railway, Chhatrapati Shivaji Terminus. Advocates: Shashikant Eknath Shekade (claimant), N.D. Raje (AGP for State), A.G. Talhar (Acquiring Body). No statutes or precedents cited in the order.
What did the court decide?
Applicants permitted to withdraw the deposited amount of Rs. 4,09,082 with accrued interest on furnishing undertaking to the satisfaction of the Registrar (Judicial); delay of 633 days in preferring the appeal condoned; first appeal admitted and to be listed for final disposal on 12.02.2026; ad interim relief confirmed.