Nilesh S/O Narendra Uplopwar v. Maha. State Power Generation Co. Ltd., (Mahagenco), Thr. Managing Director, Mumbai and Ors.
Case brief
What is this about?
Employee transfer challenge - Maharashtra State Power Generation Co. Ltd.; transfer order dated 02.06.2025 by Chief General Manager (HR); reliance on Circular dated 20.03.2025 excluding employees whose wards study in 10th-12th standards from transfer list; petitioner's name newly added to transfer list; notice for final disposal returnable 17.07.2025; service by all permissible modes permitted; interim order, no merits decided; Nagpur Bench, coram Sambre & Deshmukh JJ.
What did the court decide?
Interlocutory order only: notice for final disposal issued to the respondents, returnable on 17.07.2025; in addition to regular mode of service, service by all permissible modes is granted. No final adjudication on merits. ¶12