Ms Agra Engineering Co. v. Shree Bombay Cotton Mills Estate Pvt. Ltd.
Case brief
What is this about?
W.P. No.16833 of 2024, Bombay High Court, Madhav J. Jamdar J., decided 07-01-2025. Article 227 petition by M/s Agra Engineering Co. (defendant firm and partners) against Small Causes Court, Mumbai orders rejecting condonation of delay, acceptance of written statement, and leave to deposit rent arrears in R.A.E. & R. Suit No. 255 of 2019 (M/s Shree Bombay Cotton Mills), and revisional confirmation by the Appellate Bench in Revision Applications 39-41 of 2024 dated 02-05-2024. Writ allowed; impugned orders quashed; sufficient cause found in partnership dispute and custody of premises keys with Prothonotary (04-05-2018 to 25-04-2023); costs Rs.2,50,000/-; arrears with interest Rs.12,70,792/-; Exhibit 22 limited to arrears, future-rent deposit left open.
What did the court decide?
Writ Petition allowed in terms of prayer clause (a): Orders dated 02.05.2024 in Revision Application Nos. 39-41 of 2024 and Orders dated 04.11.2023 on Exhibit Nos. 20-22 in R.A.E & R Suit No. 255 of 2019 quashed and set aside; Exhibit Nos. 20-22 applications allowed; Petitioners to pay costs of Rs.2,50,000/- within 15 days (Rs.1,00,000/- already deposited pursuant to the Order dated 4th December 2024, withdrawable by Respondents with accrued interest; balance Rs.1,50,000/- within 15 days); arrears of rent with interest of Rs.12,70,792/- to be paid within one month, without prejudice to the rights and contentions of both parties; liberty to file fresh application regarding deposit of monthly rent from 1st January 2025, contentions kept open.