Hitachi Rail Sts India Pvt. Ltd., Bengaluru, Thr. Authorized Representative, Mr. Nillohit Dey v. Union of India, Thr. South East Central Railway, Nagpur Thr. Chief Signal and Telecom Engineer
Case brief
What is this about?
Computation of time limits — exclusion of the first day where period runs 'from' a date; day of LOA issuance treated as day 'zero'; Section 9 General Clauses Act 1897; performance guarantee / bank guarantee submission window (21 days extendable to 60 days); termination/cancellation of railway tender LOA (South East Central Railway, Nagpur Division — Wadsa, Armori, Kondhala, Gadchiroli Electronic Interlocking works); Hitachi Rail STS India Pvt. Ltd. v. Union of India & Ministry of Railways, WP 1109/2025 (BHC-Nagpur, DB, 29/07/2025); arbitration clause no bar to entertaining writ on a narrow legal issue; relied on Jai Durga Enterprises 2021 SCC OnLine Del 2446; refers to Tarun Prasad Chatterjee (2000) 8 SCC 649, Econ Antri (2014) 11 SCC 769, Frank Anthony Public School (1984) 6 DRJ 47. Neutral citation: 2025:BHC-NAG:7589-DB.
What did the court decide?
Writ petition allowed; impugned termination of LOA No. S&T/Con/NGP/SECR/734/2025/74 dated 25.02.2025 quashed and set aside; Rule made absolute; no costs.