Wellwisher Infra LLP and Anr. v. Khopoli Municipal Council and Ors.
Case brief
What is this about?
Well Wisher Infra LLP v. Khopoli Municipal Council & Ors., W.P. 10412/2024 (Bom HC, 05-02-2025, Kulkarni & Sethna JJ.). Keywords: Commencement Certificate extension; Section 48 MRTP Act; Regulation 2.2.14 UDCPR; interest waiver; 8.5% p.a.; 20%/80% installment split; Occupation Certificate; MahaRERA registration; RERA; GR compliance; Article 226; certiorari; mandamus; Real Estate (Regulation and Development) Act 2016; disposed without examining merits; no costs. Relevant for: procedural route for extension/renewal of a CC before a municipal council; UDCPR interest treatment on premium installments; developer petitions where RERA registration is obstructed by municipal observations; consent-based disposal with timelines (1 week / 10 days / 45 days).
What did the court decide?
Petition disposed of in terms of the recorded order without examining merits: (i) petitioner to furnish a complete set of documents to KMC within one week (besides Exhibit N); (ii) petitioner to apply for extension of the Commencement Certificate within 10 days, KMC to consider it in accordance with law and decide within 45 days; (iii) liberty to apply for waiver of interest under Regulation 2.2.14 UDCPR for the affected period, to be considered by the appropriate officer, with all contentions expressly kept open; (iv) upon grant of extension, KMC to communicate it within one week to the authority under the Real Estate (Regulation and Development) Act, 2016, with a copy to the petitioner; no costs. The monetary prayers (g) and (g-1) were not granted as such.