Dipak Pralhad Chavan v. State of Maharashtra; Writ Petition No.10293 of 2025; High Court of Judicature at Bombay, Circuit Bench at Kolhapur; Coram M.S. Karnik & Sharmila U. Deshmukh, JJ; decided 17 October 2025; implementation of Government Resolution dated 30.09.2024; issuance of work orders; 47 sanctioned works; 24 works awaiting final State sanction; 23 works pending scrutiny; twelve-week compliance directions; petition disposed of.
What did the court decide?
Petition disposed of with time-bound directions: Respondents No.1 to 3 to take necessary steps on the balance 23 works within twelve weeks; Respondent No.1 to take necessary decision on the 24 works submitted for final sanction of the State Government within twelve weeks. ¶21