Neamat Developers Pvt. Ltd. v. Municipal Corporation of Greater Mumbai and Anr.
Case brief
What is this about?
Restoration of writ petition dismissed for non-removal of office objections; condonation of 217 days' delay; conditional costs of Rs.10,000/- to High Court Law Library; removal of office objections within four weeks; Neamat Developers Pvt. Ltd. v. Municipal Corporation of Greater Mumbai & Anr.; Interim Application No.3556 of 2024 in Writ Petition (L) No.16172 of 2021; Bombay High Court O.O.C.J.; Gadkari and Khata, JJ.; 23-01-2025.
What did the court decide?
Restoration of Writ Petition (L) No.16172 of 2021 in terms of prayer clauses (a), (b) and (c), subject to payment of Rs.10,000/- as costs to the High Court Law Library within two weeks of uploading of the Order, and removal of office objections within four weeks from the date of payment of costs. ¶25