Shree Anukul Industries Pvt. Ltd. v. Maharashtra Jeevan Pradhikaran
Case brief
What is this about?
Bombay High Court, Ordinary Original Civil Jurisdiction, Commercial Division; Interim Application No.3456 of 2025 in Commercial Suit No.133 of 2024; Shree Anukul Industries Pvt. Ltd. v. Maharashtra Jeevan Pradhikaran & Anr.; condonation of delay of 164 days; amendment of plaintiff's name; Ministry of Corporate Affairs change-of-name certificate; service of Writ of Summons; prayer clauses (a), (b) and (c); JITENDRA JAIN, J.; decided 7 October 2025.
What did the court decide?
Delay of 164 days condoned; plaintiff directed to serve the Writ of Summons within four weeks; leave granted to amend the name of the plaintiff (amendment within four weeks, amended copy to be served on defendants); Interim Application allowed in terms of prayer clauses (a), (b) and (c). ¶¶16