Condonation of delay of 8 years 286 days in filing First Appeal (ST) No. 2461 of 2022 against award dated 17-01-2013 in LAR No. 9 of 2004 (District Judge, Pune); reliance on Ningappa Thotappa Angadi v. Special Land Acquisition Officer, Civil Appeal No. 9415 of 2019; conditional condonation with undertaking waiving interest on enhanced compensation and statutory amount for delay period; appeal admitted; land acquisition notification dated 04-07-1991 under Section 4 of the Land Acquisition Act; Village Kalas, Taluka Indapur, District Pune; New Mula Mutha Right Bank Canal; Bombay High Court; Rajesh S. Patil, J.; Interim Application No. 339 of 2024.
What did the court decide?
Delay of 8 years and 286 days in filing the First Appeal condoned; Interim Application No. 339 of 2024 allowed in terms of prayer clause (B), subject to an undertaking to be filed within four weeks that the Applicants will not claim interest on the enhanced compensation or the statutory amount for the delay period; First Appeal (ST) No. 2461 of 2022 admitted with directions regarding the private paper-book and R & P. The appeal itself remains pending, not finally decided.