Shree Ganeshay Seva Sanstha Om Sai Ram Niwas Chawl and Ors. v. Municipal Commissioner Vasai Virar Municipal Office and Ors.
Case brief
What is this about?
Bombay High Court PIL 112 of 2022 (with IA 1939 of 2024), decided 23 April 2025, Coram Alok Aradhe CJ and M. S. Karnik J. Keywords: unauthorized construction; demolition direction; Collector Palghar; Vasai Virar Municipal Corporation; Tahsildar Vasai; Survey No. 251 Hissa No. 3 Village Achole, Taluka Vasai, Nalasopara (E), District Palghar; State Government land; Societies Registration Act 1860; action taken report; order dated 24 November 2022; four-month timeline; petitioners' own alleged illegal construction; respondent nos.8 and 9; PIL disposed.
What did the court decide?
PIL disposed of with directions to the Collector, Palghar to afford a hearing to the petitioners and respondent nos.8 and 9, decide whether the construction on Survey No. 251, Hissa No. 3, Village Achole, Taluka Vasai, Nalasopara (E), District Palghar is unauthorized, remove it if found unauthorized, and also examine any unauthorized construction carried out by the petitioners, bearing in mind the order dated 24 November 2022, within a period of four months; interim application(s) disposed of.