Karbhari Bapurao Dugane v. the State of Maharashtra and Ors.
Case brief
What is this about?
Enhancement of land acquisition compensation; annual escalation 10% per annum with cumulative effect; parity/uniform rate for identical lands in different villages acquired for the same project (cluster of villages); 'Nimnna Dudhana' project; village Mapegaon, Taluka Partur, District Jalna; notification under Section 4 dated 11.07.2002; award under Section 11 dated 11.02.2006; rates per Are for dry land, seasonal irrigated land, irrigated land and pot kharab land; belting system objection rejected; acquiring body led no evidence and filed no appeal; First Appeals before High Court of Bombay, Aurangabad Bench; Shailesh P. Brahme, J.; Huchanagouda applied (escalation with cumulative effect); Ali Mohammad Beigh AIR 2017 SC 1518 followed (parity); Bhule Ram distinguished; enhanced rates Rs.4426/-, Rs.2213/-, Rs.6639/-, Rs.8852/- per Are; deficit court fees; no interest or statutory benefits for delayed period.