Shabbir Kasamji Kanchwala v. M S G F Reality Private Limited
Case brief
What is this about?
Bombay High Court, Abhay Ahuja, J., 15-01-2025; Contempt Petition No.39 of 2024 in CP No.155 of 2019 in Commercial Suit No.1100 of 2018; Shabbir Kasamji Kanchwala v. G.F. Realty Pvt. Ltd. & Anr. (Sayeed R. Sheikh, Respondent no.2 / Director of Respondent no.1); breach of Consent Terms dated 04.11.2020 and undertakings; non-delivery of possession of commercial units 401 and 1001; reply affidavit dated 12.12.2024 citing Adani electricity connection, MCGM removal of two trees and outstanding property-tax assessment bills as causes of delay in Occupation Certificate application; undertakings accepted by Court: soft / fit out possession within two weeks, transit rent and delay compensation payable till Occupation Certificate obtained from MCGM, Occupation Certificate application to be endeavoured by 31.03.2025; earlier CP 155/2019 removed from board as wrongly listed; Contempt Petition disposed.