V.I.D.C., through Executive Engineer, Purna Medium Project Division, Amravati v. Smt. Kalpana Suresh Gawande and Others
Case brief
What is this about?
Interlocutory civil application before Bombay High Court, Nagpur Bench; land acquisition Award; stay of execution; withdrawal of 75% of amount deposited by Appellant (VIDC, Achalpur) with accrued interest; 50% on usual undertaking and 25% on solvent surety/security; parity with order dated 2/12/2024 in CAF No. 3477/2024 in First Appeal No. 836/2023; same village, same project; Special Power of Attorney dated 21/1/2025; equal proportionate remittance to claimants; application allowed and disposed of.
What did the court decide?
Respondent Nos.1 to 3 permitted to withdraw 75% of the amount deposited by the Appellant with accrued interest (50% on usual undertaking; 25% on solvent surety/security); Respondent No.3 to act for Respondent Nos.1 and 2 under the Power of Attorney, with the amount remitted in equal proportions to Respondent Nos.1 to 3; Civil Application disposed of accordingly.