Special Project Division, Thr. Its Executive Engineer, v.I.D.C., Amravati v. Dattaraya Prabhakar Keche and Others
Case brief
What is this about?
Withdrawal of deposited acquisition compensation — 50% of total compensation released with accrued interest on usual undertaking; Registrar (J) to transmit amount within six weeks on undertaking and bank details; Special Project Division thru Executive Engineer Amravati v. Dattatraya Prabhakar Keche; CAF 2549/2025 in FA(ST) 25213/2024; Nagpur Bench; Joshi J.; decided 26.08.2025.
What did the court decide?
Permission to the applicant/respondent No.1 to withdraw 50% of the total compensation amount with accrued interest thereon on furnishing the usual undertaking; Registrar (J) directed to transmit the said 50% with interest to the applicant's bank account within six weeks upon furnishing an undertaking and bank account details to the Registry. ¶13