The Controller, Maharashtra State Road Transport Corporation, Station, Nagpur v. Shri. Saurabh S/O Vasanta Dhenge Thr. P.O.A. Holder Vasanta S/O Ramchandra Dhenge
Case brief
What is this about?
Withdrawal of deposited compensation amount — 75% with proportionate accrued interest permitted — appellant's objection (The Controller, MSRTC, Nagpur) held devoid of substance — usual undertaking to Registrar (J) — transfer to applicant's bank account within six weeks — Civil Application 2283/2025 in First Appeal Stamp 238/2025 — Nagpur Bench, Bombay High Court — order dated 05-08-2025 — Abhay J. Mantri, J.
What did the court decide?
The applicant is permitted to withdraw 75% of the deposited compensation amount with proportionate accrued interest, subject to furnishing a usual undertaking to Registrar (J); Registrar (J) is directed to transfer that amount with interest to the applicant's bank account within six weeks of furnishing the undertaking and bank account details. ¶15