Tapi Irrigation Development Corporation through Its Executive Engineer Girna Cannel v. the Collector Jalgaon through Special Land Acquisition Officer 1 and Ors.
Case brief
What is this about?
Condonation of delay; first appeal (FAST); land acquisition; Tapi Irrigation Development Corporation v. Collector Jalgaon; conditional deposit of amount; four weeks extension with accrued interest; automatic vacation of ad-interim relief; appeals admitted; Aurangabad Bench; Shailesh P. Brahme, J.; order dated 01.08.2025.
What did the court decide?
Condonation of delay in preferring the first appeals, conditional on deposit of the amount as ordered by the Court within the extended period; four weeks' further time granted as a last indulgence for deposit with accrued interest; ad-interim relief to continue meanwhile and to stand vacated automatically if the deposit is not made; first appeals admitted; learned AGPs waive service of notice for respondents/State; Record and Proceedings called for from the concerned Court; parties at liberty to file relevant papers.