Vijaykumar Chandgdeo Gaikwad v. the Executive Engineer Medium Project Division Osmanabad and Other
Land acquisition compensation – Partial release
Case brief
What is this about?
Bombay High Court, Aurangabad Bench — Civil Application No. 2003 of 2025 in FA/3244/2016, decided 06-05-2025 by Shailesh P. Brahme, J. Vijaykumar Chandgdeo Gaikwad v. The Executive Engineer, Medium Project Division Osmanabad — disbursement of additional 10% of deposited compensation amount with accrued interest; earlier order dated 21.09.2017 had permitted 50% withdrawal on undertaking and solvent surety; follows common order dated 22.10.2021 permitting 10% withdrawal on undertaking to Registrar (Judicial) in similarly situated matters; application opposed by Respondent No.1/acquiring body but allowed in terms of prayer clause B. Keywords: land acquisition, compensation deposit, partial disbursement, 10%, undertaking, acquiring body, Registrar (Judicial).
What did the court decide?
Civil application allowed in terms of prayer clause 'B', i.e., disbursement of further 10% of the deposited amount with accrued interest.