Rudra Super Structures LLP v. Aditya D. Goyal and 2 Ors.
Case brief
What is this about?
Consensual reference to sole arbitrator; Bombay High Court OOCJ; Somasekhar Sundaresan J.; 3 Feb 2025; CARBP 554/2021 & ARBP 19/2024 disposed; Section 9 Arbitration and Conciliation Act 1996; Shanay Shah appointed Sole Arbitrator; arbitration clause Clauses 9-14 of Agreement dated 15.02.2020; Development Agreement without arbitration clause; non-signatory Prashant Parekh/Parikh consented through counsel Ms. Mistry; Section 11 Application (L) No.21664/2023 shown disposed; merits expressly kept open; disclosure statement u/ss.11(8) and 12(1); interim-measure applications permitted u/s.17; arbitral costs shared equally initially; parties Aditya Dharmendra Goyal v. Rudra Super Structures LLP; advocates Mayur Khandeparkar, K.H. Holambe Patil, Ankur Pahade.
What did the court decide?
Both petitions finally disposed of by consensual reference of all disputes and differences to Mr. Shanay Shah, Advocate, appointed Sole Arbitrator (Office: No.17-A, 4th Floor, Surya Mahal, Burjorji Bharucha Marg, Fort, Mumbai - 400 023; email [email protected]). Directions: Petitioner's advocates to communicate the order to the arbitrator within one week of upload and provide parties' contact particulars; arbitrator to forward the statutory disclosure statement under Sections 11(8) read with 12(1) within two weeks; parties to appear before the arbitrator and provide valid e-mail/mobile/landline contacts of their advocates, communications to such e-mails constituting valid service; arbitral costs and fees borne equally in the first instance, subject to any final Award on costs; each party at liberty to apply under Section 17 of the Act; all merits issues expressly kept open.