M/S Prashant Construction, Nagpur through Prop., Prashant Prabhakar Deshmukh v. the Corporation of City of Nagpur through Its Municipal Commissioner, Nagpur
Case brief
What is this about?
Contractor's suit for withheld bills was dismissed as time-barred by the first appellate court despite a trial court decree. In second appeal, the High Court held the Corporation's general body resolution releasing contractors' payments amounted to a written promise to pay a time-barred debt under Section 25(3) Contract Act, restoring the decree.
What did the court decide?
Judgment and decree dated 05-07-2018 in RCA No. 774/2012 set aside; decree dated 21-04-2011 in SCS No. 258/2007 restored; no costs.