Nish Developers P Ltd. v. Nareshkumar Shantilal Jain and Ors.
Case brief
What is this about?
A developer sought impleadment in a writ petition, claiming it was unfairly blamed by the petitioners. The court allowed the interim application, joining the developer as 5th respondent, with directions to amend, file a reply and list the matter.
What did the court decide?
Applicant impleaded as 5th Respondent; amendment by 11 March 2024 without reverification; reply permitted by 1 April 2024.