Govindrao Laxmanrao Mehatre Thr. Poa S Mehatre v. the Executive Engineer Bembla Project, Vidc, Awadhutwadi and Others
Case brief
What is this about?
First appeal against award in land acquisition case. Court applied principle of parity with Supreme Court settlements in similar cases to enhance compensation to Rs. 1,39,500 per hectare along with statutory benefits, setting aside the Reference Court's award.
What did the court decide?
Enhanced compensation awarded at Rs. 1,39,500 per hectare along with statutory benefits as per terms of settlement in referenced Supreme Court cases.