Gmidc Aurangbad through Executive Engineer Minor Irrigation Divn Latur v. the State of Maharashtra and Anr.
Case brief
What is this about?
First appeals by GMIDC against a reference court's enhancement of land acquisition compensation. Applying State Government Resolutions of 2016-17, enhancements within four times were not challengeable, so appeals lacked merit; interest was modified to run from the date of award per precedent, and appeals were disposed of.
What did the court decide?
Award modified so interest is granted from date of award; State to deposit amount within eight weeks before Reference Court for withdrawal by original claimants.