The Executive Engineer, Khadakpurna Project Division, V.I.D.C. Deulgaon Raja, Buldana v. Nivrutti Dnyandev Dandge (Deshmukh) and Others
Case brief
What is this about?
Application to condone a 1319-day delay in filing a cross objection on an award of enhanced land acquisition compensation dated 05.04.2014. The court condoned the delay, barred statutory benefits including interest for the delayed period per the NOIDA precedent, admitted the cross objection, and directed the appeal paper book within three weeks.