Avinash Tukaram Ingale v. the Executive Engineer, Minor Irrigation Division Thr Lift Irrigation Division,Osmanabad and Ors.
Case brief
What is this about?
Claimant in a land acquisition appeal sought modification of an earlier order permitting partial withdrawal of compensation against a bank guarantee. The court allowed the application, permitting withdrawal of the remaining 25% with accrued interest on furnishing solvent surety/security, consistent with similar claimants' applications already allowed.
What did the court decide?
Clause II modified: applicant may withdraw remaining 25% of amount with accrued interest on furnishing solvent surety/security to the satisfaction of Registrar (Judicial).