Ex. Engineer M.I.Beed Now Beed Irri.Div. Beed Under Gmidc Aurangabad and Ors. v. Baliram Raosaheb Chavre and Ors.
Case brief
What is this about?
Condonation of delay in first appeals; FAST appeals 2024; Acquiring Body appeal against Reference Court compensation-enhancement order; Ex. Engineer M.I. Beed Irrigation Division under GMIDC Aurangabad; Tarde and Dhapate claimant-side respondents; Bombay High Court Aurangabad Bench; Kishore C. Sant, J.; order dated 10.10.2024; delay condoned; first appeals registered; stay on execution and operation of impugned judgment and award conditional on depositing entire amount with interest within 12 weeks; Civil Applications 2130-2147, 10090-10091, 3861-3862 of 2024.
What did the court decide?
Delay in filing each appeal condoned; Civil Applications disposed of; First Appeals ordered to be registered; execution and operation of the impugned judgment and award stayed subject to deposit of the entire amount with interest within 12 weeks. ¶82