Rounak Industries Thr His Represeantative v. the State of Maharashtra through Its Secretary and Others
Case brief
What is this about?
Bombay High Court, Aurangabad Bench; interim order dated 15 March 2024; Writ Petition No. 1083 of 2024; Dnyanoba Rangnath Munde v State of Maharashtra; electricity transmission tower erected at earmarked place; stringing of wires connecting towers completed; no crops standing at time of stringing; no hindrance for project to proceed; challenge to two orders of District Collector Chhatrapati Sambhajinagar dated 28/02/2024 in Case No.2024/Home/CR-01 and Case No. 2024/Home/CR-02/24; civil applications for addition of parties allowed; intervenors Rounak Industries (Mahesh Harishankar Gautam) and M/s T.P. Saurya Ltd.; amendment of petition; notices waived; advocate A. M. Gaikwad on Panel of Electricity Transmission Company; coram Ravindra V. Ghuge and R. M. Joshi, JJ.; next hearing 05/04/2024 urgent orders category.
What did the court decide?
Interim directions only (writ petition not finally disposed): Civil Applications for addition of parties allowed and Petitioner directed to add the Intervenors as Respondents; notices to the added Respondents waived by their Advocates; Shri Gaikwad requested to collect the paper book, take instructions and address the Court on the next date; matter stood over to 05/04/2024 in the 'urgent orders' category; consideration of the two District Collector orders dated 28/02/2024 deferred to the next date.