Ms. Sukoon Manekia Sethi Dir. of Merint Industrial Infrastructure Private Limited v. Project Engineer (Sk),Government of India and Ors.
Case brief
What is this about?
The petition for appointment of an arbitrator to decide a claim for escalation was dismissed. The court held that the claim was barred because the petitioner failed to make a demand within 120 days as required by the arbitration clause, accepted the final bill as full and final settlement, and the contract explicitly prohibited escalation payments for extended periods.