M/s Borse Brothers Engineer and Contractor Pvt. Ltd. Through its Director Shri Jitendra Bhatu Sonawan v. The Dhule Municipal Corporation Through the Municipal Commissioner
Case brief
What is this about?
Arbitration Application No. 41 of 2024; High Court of Bombay, Aurangabad Bench; decision dated December 17, 2024; R.M. Joshi, J.; Applicant M/s Borse Brothers Engineer And Contractor Pvt Ltd (Director Shri Jitendra Bhatu Sonawan); Respondent Dhule Municipal Corporation (through Municipal Commissioner); Advocate A. K. Gawali for Applicant; notice issued returnable 20.01.2025; liberty to serve by alternate permissible mode and file affidavit of service; notice-stage order only, no merits, no statute or precedent discussed.
What did the court decide?
Interim procedural direction only: notice issued to Respondents returnable on 20.01.2025, with liberty to the Applicant to serve the Respondents by any other permissible mode of service and to file an affidavit of service before the next date. No merits adjudicated. ¶11