to a new contractor. This itself shows that at least some part of the contract work was completed by the plaintiff. On what basis the Zilla Parishad Ratnagiri, which is the government body gave a fresh tender work for the balance work to a new party has not been brought on record neither they have brought on record how much part of the work was balance, in order to float a new tender for the balance work. Clause 3(c) puts this burden on the Zilla Parishad Ratnagiri to measure the work before floating the new contract for the balance work. Since, the Zilla Parishad Ratnagiri even though they had measured the work, nothing has been brought on record to prove the said fact in their evidence, neither they have stated anything on that lines in their written statement. Hence, for Zilla Parishad Ratnagiri not been able to prove the said fact, there is no fault in the statement made by the Plaintiff in evidence that 75% of the work has been completed by him. The plaintiff has also specifically in para no.5 of the Plaint specially stated that he has completed 75% of the tender work. Para No.5 reads as under: