M/S. Manoj Kumar Construction Company, Aurangabad v. the Godawari Marathwada Irrigation Corporation through Executive Engineer, Parbhani
Case brief
What is this about?
The bench directed the respondent corporation to deposit the remaining 50% of the arbitral award pending the final hearing of the appeals. The court ordered the amount to be invested in fixed deposits and granted liberty to the applicants for withdrawal if the appeal remains undecided by the specified date.
What did the court decide?
Remainder 50% amount of Rs.56,45,218/- to be deposited within 30 days; invested in FR with renewal; liberty to apply for withdrawal if appeal not decided by 30/04/2023.