What is this about?
This High Court set aside an Arbitrator's order terminating arbitral proceedings. The Arbitrator had concluded the petitioner abandoned its claim due to inactivity and lack of participation in a separate but related arbitration. The Court held that the petitioner's non-participation in the other proceeding did not imply abandonment of its own distinct claim and remanded the matter for the Arbitrat
What did the court decide?
The impugned order terminating the arbitral proceedings was set aside. The Sole Arbitrator is directed to continue the reference and conclude proceedings within six months.