Oil and Natural Gas Corporation Ltd. v. Gol Offshore Limited Cin No. L11200MH2005PLC154793
Case brief
What is this about?
The Bombay High Court, in an interim application, allowed the condonation of a 87-day delay in filing an affidavit in proof of debt against a company in liquidation, directing the Official Liquidator to adjudicate the claim.
What did the court decide?
Delay of 87 days in filing affidavit in proof of debt was condoned; Official Liquidator directed to adjudicate applicant's claim.