State of Maharashtra through the Chief Engee. (Spl.Project) PWD and Anr. v. Bharat Constructions
Case brief
What is this about?
Arbitration Petition challenging majority award granting compensation for delay. Court held Section 34 does not preclude reviewing dissenting views but affirmed award under narrow scope. Award based on accepted formula and evidence appreciation was upheld.
What did the court decide?
Petition dismissed; no interference with the leading and majority of the Arbitral Award; pending applications disposed of.