Alex J. Fernandes v. the State of Goa, Thr. the Cheif Secretary and 7 Ors.
Case brief
What is this about?
Held that unauthorized constructions in a CRZ area by Respondents 7 and 8 violated the law due to lack of permissions and occupancy certificate. The Court ordered immediate demolition, disconnection of water and electricity, and sealing of premises. An affidavit and resolution regarding the demolition order were annexed and considered.
What did the court decide?
Directed demolition of the illegal structure, disconnection of water and electricity, and sealing of premises within ten and fifteen days.