Bharati Defence and Infrastructure Ltd. v. Andaman and Nicobar Administration Port Blair
Case brief
What is this about?
High Court granted extension of the mandate of the arbitral tribunal for one year in multiple arbitration petitions. The court applied Supreme Court orders excluding the pandemic period (March 15, 2020 to October 2, 2021) from limitation calculations under Section 29A of the Arbitration and Conciliation Act.
What did the court decide?
Extension of the mandate of the arbitral tribunal for a period of one year from the date of the order. The period from March 15, 2020 to October 2, 2021 is excluded in computing the period under Secti