Shivkumar Vitthal Gulve and Anr. v. the State of Maharshtra and Ors.
Case brief
What is this about?
High Court Bench at Aurangabad disposed of PIL PIL 36/11 regarding alleged misappropriation of funds and false measurements in water supply works at village Kharda. The Court terminated proceedings noting works were completed, payments were legitimate, and the Grampanchayat recorded satisfaction of implementation in 2017. No costs awarded.
What did the court decide?
Proceedings terminated noting contractor completed works, payments were not false, and Grampanchayat recorded satisfaction of scheme implementation.