The Executive Engineer Works Division Xv (Nh) Pwd, Govt. of Goa and 3 Ors., v. P. B. Ibrahim.
Case brief
What is this about?
A roadworks contractor challenged security forfeiture and delay compensation for incomplete centre-line painting. The court held time was not of the essence and ordered repayment of the security and compensation with 6% interest. Other claims were rejected. Both cross-appeals were partly allowed.
What did the court decide?
Repayment of forfeited security and recovered compensation with 6% annual interest from suit institution until payment; interest on the existing award reduced to 6%.