type 'D' quarters comprised in 26 three storey buildings in the same campus at Aswapuram, Khammam District, Andhra Pradesh. The Respondent submitted its tender. Having found it to be the lowest bidder, on 27 November 2007, a Letter of Intent (LoI) was issued by the Petitioner to the Respondent. This was followed by a formal work order dated 28 December 2007. On 5 January 2008, the Respondent commenced the work at site. On 4 July 2009, the Respondent requested for extension of time upto 28 February 2010 for completion of the work. In between, correspondence ensued between the parties. The Petitioner took up a position that the progress of the work was not upto the mark and if proper progress was not made and the work was not completed in time, action for rescinding the contract would be initiated under Clause 3 of General Conditions of Contract (“GCC”). The Petitioner, nevertheless, by its order dated 31 August 2009, extended the time for completion of work upto 31 January 2010 subject to levy of compensation under Clause 2 of GCC. Finally, the work was completed by the Respondent on 15 June 2010. The Petitioner, on its part, granted extension of time upto that date, subject again to levy of compensation under Clause 2 of GCC. The mechanism for levy of compensation, including show cause notice under Clause 2 of GCC, was thereupon initiated by the Petitioner. Finally, by its letter dated 2 December 2010, the Petitioner informed the Respondent about the levy of compensation. The Respondent protested against such levy and signed the final bill prepared by the Petitioner under protest. Since the controversy pertaining to the Respondent's dues under the final bill and levy of compensation could not be resolved between the parties, the Respondent invoked the arbitration agreement forming part of the contract and that is how the reference was made to the sole arbitrator. The learned arbitrator,