Sangamner Loni Infrastructure Pvt. Ltd. through Its Managing Director Mohammad Israil v. the Governor of Maharashra through Its Executive Engineer and Others
Case brief
What is this about?
In a writ petition seeking compensation for a BOT project, the Court permitted an amendment to add the Chief Engineer as a respondent. It disposed of the petition by directing the added respondent to decide the claim within four months and the primary respondent to decide any new representation within eight weeks.
What did the court decide?
Petition disposed by directing the Chief Engineer to decide the claim within four months and the Executive Engineer to decide a new representation within eight weeks.