Bhausaheb Sahebrao Mane v. the State of Maharashtra and Another
Case brief
What is this about?
Petitioner challenged rejection of Project Affected Person certificate for acquired land (K.V. sub-station). Court quashed rejection, directing Director to act in line with W.P. No. 2816 of 1997 within 12 weeks.
What did the court decide?
Quashed the order dated 10th August, 2016; directed the Deputy Collector to pass afresh orders within twelve weeks.