Vidyasagar Dube v. the Commissioner Mcgm and 6 Ors.
Case brief
What is this about?
In this PIL, the petitioner challenged development permission granted to Respondent No. 6 due to alleged non-compliance of condition no. 16. The court observed the condition was complied with belatedly, noting interest was charged and security forfeited by the Authority. The court held not to take separate action for delay and dismissed the petition.
What did the court decide?
The court dismissed the petition and expressed no inclination to proceed further as the grievance was redressed.