State of Goa, Rep. by the Chief Secretary, Govt. of Goa and Anr., v. Delcon Engineering.
Case brief
What is this about?
In a first appeal regarding extra civil works executed after the original contract expired, the High Court upheld the trial court's finding that GSR 1997 rates applied. The appeal was partly allowed to correct a mathematical error in the computation of the awarded sum.
What did the court decide?
First Appeal partly allowed; impugned judgment modified to reflect correct computation of Rs.16,61,710/- along with 6% interest; decree confirmed otherwise.