The State of Maharashtra v. Moreshwar Waman Sane
Case brief
What is this about?
The High Court of Judicature at Bombay allowed an appeal against the Reference Court's compensation award. The court upheld the compensation amount of Rs.2000/- per acre but modified the interest award, ruling it must run from the Section 4 Notification date.
What did the court decide?
Enhanced compensation of Rs.2000/- per acre maintained; interest under Section 23(1A) payable from Section 4 Notification date.