M/S. Vaishnovi Construction and Tbpr Infra Project Pvt. Ltd., Thr. T. Gangadhar Rao v. Vidarbha Irrigation Development Corporation Sinchan Seva Bhavan Nagpur Thr. Executive Director
Case brief
What is this about?
In a petition challenging penalty imposition for non-completion of work, the Nagpur Bench noted the dispute between an extension claim and a proposal to rescind the contract. It referred to Supreme Court precedent regarding penalty liabilities and refused to decide disputed questions, continuing an interim order. The petition was disposed of without costs.
What did the court decide?
Previous interim order restraining coercive steps continued; respondents directed to take final decision on resiliation or extension within three weeks.